Keep up with this year’s renovation projects happening at Roadhaven Resort

Activities Office (Rec hall)

PROJECT STATUS
70%

Project Start: April 1, 2022

The Activities Office is moving from the Teton Building into the Rec Hall. The newly built office will be at the north main entrance near the restrooms. A walk-up window will be available both inside and outside the Rec Hall for fast and easy convenience to purchase tickets for concerts and events.

What’s been done:

  • Old space emptied; items relocated temporarily to Rec Hall
  • Counter removed in new space
  • Cabinets removed in new space
  • Rough-in framing
  • Rough-in service window
  • Electrical rough-in
  • Rough In Inspection

What needs to be done:

  • Insulation
  • Drywall
  • HVAC balance
  • Paint
  • Baseboards
  • Install cabinets
  • Hang doors
  • Reset furniture and equipment

Billiards (teton building)

PROJECT STATUS
70%

Project Start: April 1, 2022

1, 2, 3, Floor! Billiards is getting the floor repaired, leveled, and all new carpet. The pool tables are currently being stored in the Rec Hall. Once renovations are complete, six tables will be getting new felt.

What has been done:

  • Old space emptied; items relocated temporarily to Rec Hall
  • Replaced missing installation in the ceiling
  • Carpet removal
  • Glue removal
  • Relocated spotlights
  • Relocated cameras
  • Leveled expansion joints
  • Wall demolition
  • Trophy case moved and mounted
  • Custom lockers built
  • Rough-in new wall
  • Cut in for exterior doors
  • Electrical Rough In
  • Rough In Inspection
  • Drywall
  • Built Storage Cabinet

What needs to be done:

  • Texture
  • Paint
  • Hang exterior doors (2)
  • Drop ceiling repairs
  • Floor covering
  • Exit lights
  • Smoke detectors
  • Hiking club cabinet relocation
  • Install custom lockers
  • Reset cameras
  • Reset billiards tables
  • Reset Benches
  • Reset Desks

CANTINA ROOF

PROJECT STATUS
100%

Project Start: April 18, 2022

The Cantina roof is getting a new underlayment barrier and new fascia this summer.

CARD ROOM (Aztec building)

PROJECT STATUS
95%

Project Start: April 1, 2022

The Card Room is temporarily moved to the Dakota Room in the Apache building during renovations. Once renovations are complete the Card Room will be located in the Aztec building (in the original Fitness Center next to the Cantina).

What’s been done:

  • Old space emptied; items relocated temporarily to Rec Hall
  • New space prepped
  • Carpet removal
  • Walls coated
  • Walls patched
  • Walls textured
  • Walls painted
  • Ceiling painted
  • Data ports
  • Floor Covering
  • New outlet covers

What needs to be done:

  • New blinds -future
  • Reset furniture

CART PATH CHANGE

PROJECT STATUS
100%

Project Start: MAY 09, 2022

Cart path near tee box #1 is being rerouted so it is not in the middle of the fairway. This move will also stop mud puddles from forming in the pathway from the sprinklers.

 

Drinking Fountain Drain

PROJECT STATUS
100%

Project Start: May 24, 2022

To stop external water leakage, we are adding a drain to the drinking fountain in Phase II near the Cantina.

 

FITNESS CENTER (teton bulding)

PROJECT STATUS
60%

Project Start April 1, 2022

The Fitness Center is moving from the Aztec building in Phase II to the Teton building in Phase I. This expansion project will help accommodate future growth at Roadhaven.

What has been done:

  • Old space emptied; items relocated temporarily to Rec Hall
  • Demolition of north library wall (used to be a hallway)
  • Mirror moved
  • Floor leveling
  • Carpet removal
  • Glue Removal
  • Walls patched
  • Electrical Rough In
  • Plumbing changes
  • Modified IT closet
  • HVAC returns moved
  • New duct work added
  • New windows cut in and installed
  • Rough In Inspection
  • Insulation
  • Drywall

What needs to be done:

  • Drop ceiling repairs
  • Texture walls
  • Paint walls
  • Floor covering
  • Replace the existing door (north side)
  • Smoke detectors
  • Sink cabinet
  • Install mirror
  • Install drinking fountain
  • Installation of Murphey Beds upon arrival
  • Relocate and reassemble equipment

FRONT OFFICE

PROJECT STATUS
65%

Project Start: July 8, 2022

We will be adding approximately 85 square feet to the Front Office. This space will be utilized by our Office Manager to consult with both new and existing residents.

 

Golf Course Drainage

PROJECT STATUS
100%

Project Start: May 01, 2022

New drainage on the golf course near hold #2. This will help control ponding.

 

Grass Trap Changes

PROJECT STATUS
100%

Project Start: May 16, 2022

We extended the grass trap near the #4 tee box. This will help keep golf balls on the green and out of the lake.

 

Library (aztec building)

PROJECT STATUS
95%

Project Start: April 1, 2022

The Library is temporarily closed. All books are carefully packed and stored in the Rec Hall during renovations. Once renovations are complete the Library will be located in the Aztec building (in the original Fitness Center next to the Cantina).

What’s been done:

  • Old space emptied; items relocated temporarily to Rec Hall
  • Old shelves stripped and ready for finish
  • New space prepped
  • Carpet removal
  • Walls coated
  • Walls patched
  • Walls textured
  • Walls painted
  • Refinish old shelves
  • New outlet covers
  • Floor covering
  • Build additional shelves
  • Refinish new shelves

What needs to be done:

  • New blinds – future
  • Reset furniture
  • Members reshelve books

Pickleball Bulletin Board

PROJECT STATUS
100%

Project Start: May 2, 2022

Added a second bulletin board near the pickleball courts

 

Planter Drainage

PROJECT STATUS
50%

Project Start: May 2022

To prevent external leaking, the inside walls of the Phase I planters are being sealed and holes have been drilled in the bottom of each.

 

Teton Building Commodes

PROJECT STATUS
100%

Project Start: May 2, 2022

Replaced all commodes in women’s and men’s restrooms.

 

Turf Removal

PROJECT STATUS
100%

Project Start: May 06, 2022

Our golf maintenance crew is strategically removing unnecessary turf to reduce water usage, seed, and labor costs. We have reduced turf in years past, this summer we are working near hole #6. We will utilize some of the new open areas to rehome native plants.

 

Compare listings

Compare