Resort Projects
This page is designed to help residents track projects taking place across the community.
The Community Projects section includes routine and planned improvements that typically occur during the summer months and move forward as part of normal operations, regardless of any special assessment. The Club Projects section tracks club projects funded by the clubs.
The Assessment Projects section tracks projects specifically funded by the approved special assessment. These are separate, designated improvements tied directly to that funding and are presented independently for clarity and transparency.
COMMUNITY PROJECTS
2026 Summer Projects at Roadhaven Resort
DAKOTA ROOM
- Project Outline
Back door jamb repairs are being completed in the Dakota Room to address wear and restore proper function. This work will improve door alignment and ensure a secure, reliable entry point.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
GREEN ROOM
- Project Outline
Work is pending in the Green Room to remove the existing tint and apply new tint to the sliding glass doors. This update will improve appearance while enhancing light control and overall comfort within the space.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
PERIMETER WALL
- Project Outline
Exterior painting of the perimeter wall along Buena Vista and 16th Ave is scheduled as an upcoming project to refresh the appearance of the property. This work will improve overall curb appeal and help protect the wall from weathering once completed.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
CURB WORK
- Project Outline
Curb work to touch up yellow caution striping throughout the resort is scheduled as an upcoming project. This will improve visibility and reinforce safety across high-traffic areas once completed.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
PHASE I SHOWERS
- Project Outline
Grout work in the Phase I men’s and women’s showers is scheduled as an upcoming project to address wear and maintain proper sealing. This will improve durability, cleanliness, and overall appearance once completed.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
REC HALL
- Project Outline
Work will include professional cleaning and fire-retardant treatment of the stage curtains, cleaning of Rec Hall chairs, and reconstruction of the cabinets located beneath the pass-through window in the Rec Hall kitchen area. These improvements are intended to help maintain the facility, extend the life of existing assets, and improve the overall experience for residents and guests.
- Details
- Project Status: Completed!
- Estimated Costs:Â
- Estimated Start Date:
- Date of Project Completion: May 23, 2026
BIP RESTROOM ROOF
- Project Outline
Roof repairs at the BIP restroom, including the installation of new shingles, are scheduled as an upcoming project. This work will address existing wear and help protect the structure from future weather-related damage.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
MEDICAL SHED
- Project Outline
Rebuilding the doorway at the Medical Shed is scheduled as an upcoming project to address structural wear and ensure proper access. This work will improve durability and provide a more secure, functional entry once completed.
- Details
- Project Status: Completed!
- Estimated Costs:Â
- Estimated Start Date: May 20, 2026
- Estimated Date of Project Completion: TBD
CLUB PROJECTS
The projects below are funded by the individual clubs
LAPIDARY
- Project Outline
Drain cleaning and new valve installation in the Lapidary area are scheduled as an upcoming project to improve water flow and overall system function. This work will help prevent backups and support consistent operation once completed.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
SHUFFLEBOARD
- Project Outline
Concrete painting and drain cleaning in the Shuffleboard area are scheduled as an upcoming project to refresh the space and address drainage concerns. This work will improve overall appearance and help maintain proper water flow once completed.
- Details
- Project Status: Pending
- Estimated Costs:Â
- Estimated Start Date:
- Estimated Date of Project Completion:
Special Assessment PROJECTS
The projects below cover year 1 of the 3 year special assessments projects plan
BLOCK WALL
- Project Outline
Professional evaluations are needed to identify cracks, shifting, rust, and stability issues to prevent structural failures and costly emergencies.
- Details
- Project Status: Starting Soon
- Estimated Costs: $14,000.00
- Estimated Start Date:
- Estimated Date of Project Completion:
Gas Packs & HVAC
- Project Outline
Multiple heat pumps, gas packs, and mini-splits. These aging systems are less efficient and prone to failure. Aging systems are less efficient and increasingly prone to sudden failure; Proactive replacement helps control expenses and maintain reliability.
- Details
- Project Status: Starting Soon
- Estimated Costs:
- Heat Pumps, Gas Packs, Mini Splits $96,500.00
- Estimated Start Date:
- Estimated Date of Project Completion:
EQUIPMENT
- Project Outline
Several critical pieces of equipment are currently being replaced or upgraded as part of an active project:
- The aerator is being replaced due to failure and lack of available parts.
- The greens mower is being repaired or replaced to address hydraulic issues.
- Details
- Project Status: Starting Soon
- Estimated Costs:
- Aerator $45,000.00 | Greens Mower $23,000.00
- Estimated Start Date:
- Estimated Date of Project Completion:
CULVERTS
- Project Outline
Culverts beneath this section of roadway will be replaced due to severe deterioration. Rusted-through sections have exposed underlying soil and weakened the street above, while trapped water has accelerated corrosion and increased the risk of flooding and sinkholes. This replacement work is underway to prevent roadway failure, protect public safety, and avoid costly emergency repairs.
- Details
- Project Status: Starting Soon
- Estimated Costs:Â $340,000.00
- Estimated Start Date:
- Estimated Date of Project Completion:
STREET RESEAL
- Project Outline
Streets should be resealed every 5–7 years to prevent cracking, water intrusion, and major structural failures, protecting long-term roadway investment.
- Details
- Project Status: Active
- Estimated Costs: $185,968.00
- Estimated Start Date: Apr. 06, 2026
- Estimated Date of Project Completion: Jun. 10, 2026
RESURFACING
- Project Outline
Phase II Pool, spa, and deck surfaces are failing, with cracks and material loss despite repeated patching. The deck’s rubberized surface is trapping moisture in areas, causing bubbling, staining, and ongoing deterioration. Full resurfacing and deck rehabilitation are needed.
- Details
- Project Status: Starting Soon
- Estimated Costs:
- Phase II Pool/Spa Resurface $63,800.00
- Phase II Deck $45,000.00
- Estimated Start Date: June 01, 2026
- Estimated Date of Project Completion: TBD
SALT CELL SYSTEM
- Project Outline
Current salt cells at the Phase II pool are undersized and stacked to meet demand, stressing equipment and reducing performance. A commercial-grade system is required for proper sanitation and reliability.
- Details
- Project Status: Starting Soon
- Estimated Costs: $22,360.00
- Estimated Start Date: June 01, 2026
- Estimated Date of Project Completion: TBD
SAND FILTER
- Project Outline
Five of the six filters for Phase I & Phase II pools and spas have exceeded their useful life, reducing filtration effectiveness and water quality while increasing the risk of equipment failure. Replacing them will improve system performance, enhance water quality, and improve overall skimmer effectiveness.
- Details
- Project Status: Completed
- Estimated Costs: $18,045.00
- Estimated Start Date: May 19, 2026
- Estimated Date of Project Completion: TBD
CAMERA SYSTEMS
- Project Outline
Over the past decade, more than 140 cameras have been installed throughout the resort. Because they were added gradually over many years, the system now includes a mix of equipment—ranging from older analog cameras to newer digital models. This staggered approach has created inconsistencies in technology, cabling, and platforms.
We will be transitioning to a single, standardized platform and connection type will greatly improve system reliability, streamline repairs, and enhance overall security coverage for the community.
- Details
- Project Status: Starting Soon
- Estimated Costs: $90,000.00
- Estimated Start Date:
- Estimated Date of Project Completion:
NETWORK SWITCHES
- Project Outline
Network switches across the resort are actively being replaced and standardized to improve reliability and security. These switches serve as the critical connection point between the fiber optic network and essential systems, including computers, WiFi, security cameras, gate operations, and VOIP phones.
Most of the existing switches have reached end of life and no longer receive security updates, increasing the risk of failure and cyber incidents. In addition, the system was built over time without a consistent design, making troubleshooting and management difficult. This project addresses those issues by upgrading and standardizing the network infrastructure.
- Details
- Project Status: Starting Soon
- Estimated Costs: $31,000.00
- Estimated Start Date:
- Estimated Date of Project Completion:
FIRE HYDRANTS
- Project Outline
Three fire hydrants will be replaced.
- Details
- Project Status: Active
- Estimated Costs: $31,000
- Estimated Start Date: May 22, 2026
- Estimated Date of Project Completion: TBD
WATER VALVES
- Project Outline
Isolation valves regulate water flow, allowing repairs to be completed without shutting down service to large sections. The system includes over 100 valves, with recent inspections identifying 20 that have failed or are in declining condition.
- Details
- Project Status: Active
- Estimated Costs: $150,000
- Estimated Start Date: May 27, 2026
- Estimated Date of Project Completion: TBD
Deferred Maintenance: Background and Path Forward
As we began developing the upcoming summer projects list, we reviewed the Association’s Reserve Studies from 2017 and 2023 to better understand which major repairs and replacements had been completed and which were coming due. That review quickly revealed a larger issue.
Many items identified in prior years had been deferred, temporarily repaired, or replaced with equipment already near the end of its useful life. What initially appeared to be isolated maintenance needs was, in reality, a growing backlog without a long-term strategy to fully address it.
It also became clear that the long-standing approach of minimizing quarterly assessment increases limited the Association’s ability to keep pace with aging infrastructure and adequately fund reserves.
In response, the community approved a Special Assessment to move forward with a comprehensive plan to address these needs. The projects will be carried out over a three-year period, with the majority of work taking place in Years 1 and 2, and the lake liner project scheduled for Year 3.
Together, these efforts represent a more structured and proactive approach to addressing deferred maintenance. The goal is to improve infrastructure reliability, protect public safety, and strengthen the Association’s long-term financial stability and property values.
Projects By Year:
(Project timelines may change.)
Year 1 (2026-2027)
- Equipment and Machinery
- Boom Lift
- Facilities
- Block Wall Assessment
- Heat Pumps, Gas Packs, Mini Splits
- Golf Course Equipment
- Aerator
- Greens Mower
- Infrastructure and Streets
- Culvert Repairs
- Reseal Streets
- Pools and Aquatics
- Phase I and Phase II Sand Filters
- Salt Cell System Phase II
- Technology and Security
- Cameras and Cabling
- Network Switches
- Water System
- Fire Hydrant Replacement
- Isolation Valves
Year 2 (2027-2028)
Equipment
Rec Hall Ice Machine and Condenser
Restaurant Equipment
Facilities
Common Area Flooring – Carpet/Vinyl
Exterior Paint Common Area Buildings
Interior Paint
Windows and Screens
Golf
Chemical Spray Tank for Golf Course
Golf Course Irrigation Timers
Seed Spreader
Tee Box Screen Replacement
Used Golf Carts
Infrastructure
Bridge Structural Evaluations
Concrete Repairs – Common Areas/Canal
Pools
Phase I Aquatic Building Moisture Barrier
Phase II Deck
Phase II Pool/Spa Resurface
Water
Water Fountain Replacements
Year 3 (2028-2029)
#8 Lake Liner/Asphalt/ConcreteÂ